318a White Hart Lane

Milestones

  • Principles and concepts

    January 2020

     

    -

     

    February 2020

    Gather thoughts, ideas and aspirations for the masterplan to inform design process.
  • Refined masterplan

    March 2020

     

    -

     

    Complete

    Gather more detailed community aspirations relating to elements of the refined masterplan proposals.
  • Final masterplan

    April 2020

     

    -

     

    May 2020

    Gather thoughts relating to the refined masterplan proposals. Begin a process of incorporating final community feedback into the masterplan designs
  • Planning Submission

    June 2020

     

    -

     

    Complete

    Develop and submit a planning submission, informed by residents' feedback.
  • Planning Committee recommends approval

    September 2020

     

    -

     

    Complete

    Haringey's planning committee recommends approval for our proposals
  • Site preparation

    September 2021

     

    -

     

    Complete

    Site being prepared for construction works
  • Construction

    winter 2021

     

    -

     

    In Progress

    Commencement of construction works
  • Completion of New Homes

    Autumn 2024

     

    -

     

    Upcoming

    Construction complete